Basti |
No of Houses |
Start Date |
Completed |
Handed Over |
Time Taken
(in Days) |
|
DISTRICT MUZAFFARGARH
PROJECT – 1 (PILOT PROJECT)
Basti Sardh renamed BASTI PUNJAB RANGERS |
9 |
31 AUG 10 |
9 SEP 10 |
10 SEP 10 |
10 |
|
|
|
DISTRICT MUZAFFARGARH
PROJECT – 2
Basti Gharibabad renamed GLASGOW VILLAGE |
20 x House
1 x School
2 x Mosque |
|
|
|
18 |
|
|
PROJECT – 3
Basti Shaheedabad
|
20 |
|
|
|
10 |
PROJECT – 4
Basti Perianwala renamed BASTI BHATTIABAD
|
15 |
|
|
|
11 |
PROJECT – 5
Basti Gharibabad renamed GLASGOW VILLAGE
|
40 |
|
30 OCT 10 |
3 NOV 10 |
22 |
PROJECT – 6
Basti Charroy wala
|
33 |
6 OCT 10 |
30 OCT 10 |
3 NOV 10 |
24 |
PROJECT – 7
Basti Kundi Syedan – Kot Addu
|
20 |
|
|
|
17 |
PROJECT – 8
Basti Bukhari – Kot addu
|
40 |
13 OCT 10 |
30 OCT 10 |
3 NOV 10 |
17 |
PROJECT – 9
Basti Tibba Bhattian – Kot
Addu
|
22 |
13 OCT 10 |
30 OCT 10 |
3 NOV 10 |
17 |
PROJECT – 10
Basti Habibabad
|
30 |
11 OCT 10 |
30 OCT 10 |
3 NOV 10 |
19 |
PROJECT – 11
Basti Banaewala
|
40 |
24
OCT 10 |
30 OCT 10 |
3 NOV 10 |
7 |
|
|
|
|
|
|
|
BASTI NAME
|
NO OF HOUSES
|
PROJECT STARTED
|
|
|
|
SARDARWALA |
22 |
4 NOV 10 |
UNDER CONSTRUCTION |
85 % |
|
GHARIBABAD |
30 |
4 NOV 10 |
"" |
60 % |
|
HABIBABAD |
30 |
4 NOV 10 |
"" |
50 % |
|
BANAEWALA |
20 |
4 NOV 10 |
"" |
85 % |
|
MUSLIM |
29 |
4 NOV 10 |
"" |
95 % (1 X MOSQUE) |
|
LANGHUWALA |
30 |
11 NOV 10 |
"" |
10 % |
|
LALMIR |
40 |
11 NOV 10 |
"" |
8 % |
|